Grant Details, Analysis and Evaluation
Sri Lanka Global Fund Round 6 TB Grant (SRL-607-G08-T)
as of 31 August 2010

The information provided here is based on data available from the Global Fund website. Based on that data, we provide a comparative evaluation of how each grant performed during its first 2 years (Phase 1). Performance information for later years is also provided but has not been evaluated. Aidspan is currently developing a more comprehensive evaluation methodology which will provide comparative analyses of grant performance during every phase: Phase 1 (Years 1-2), Phase 2 (Years 3-5) and Rolling Continuation Channel (RCC) covering subsequent years.

All money amounts are in US dollars. Grants are rated by Aidspan according to the following color-coded scheme:
A: On or ahead of schedule
B: Up to 3 months behind
C: 3 to 6 months behind
D: Over 6 months behind
N: Not rated

Expected versus Actual Cumulative Disbursements

COUNTRY DETAILS
Country Sri Lanka
Aidspan page for Sri Lanka Overview of grants to Sri Lanka
RELATED GRANTS
Click on the link for details of the other grant resulting from the same Proposal SRL-607-G07-T
GRANT DETAILS
Grant Number SRL-607-G08-T
Title Strengthening Tuberculosis control efforts by widening the scope of DOTS to reach the marginalized and the vulnerable populations in Sri Lanka
Round / NSA Wave Round 6 (TRP comments)
Applicant CCM
Disease Component TB
Principal Recipient Lanka Jatika Sarvodaya Shramadana Sangamaya
Recipient Type Civil Society - NGO
Official Start Date 1 January 2008
PHASE 1 - Years 1-2
Agreed Amount $957,593
Approval Date 3 November 2006
Agreement Date 21 June 2007
Status Approved. Agreement signed. 2 disbursements.
LATER PHASES
Projected Amount $3,239,999
Phase 2 Approval Date Not yet approved.
Phase 2 Agreement Date Not yet signed.
Status Not yet approved. Agreement not yet signed. No disbursements yet.
TOTAL
$4,197,592 (Phase 1 agreed + later phases)
GROUPED GRANTS
Totals for all grants arising from the same proposal
PHASE 1 - Years 1-2
Agreed Amount $4,186,195
Approval Date 3 November 2006
Agreement Date 21 June 2007
Status Approved. Agreement signed. 8 disbursements.
LATER PHASES
Agreed Amount $3,239,999
Phase 2 Approval Date 11 March 2010
Phase 2 Agreement Date 7 June 2010
Status Phase 2 approved. Phase 2 agreement signed. No disbursements yet.
TOTAL
$7,426,194 (Phase 1 agreed + later phases)
PHASE 1 EXPECTED DISBURSEMENTS
Disbursement Date Amount
1 1 Jan 2008 $0
2 23 May 2008 $697,699
3 23 Aug 2008 $697,699
4 23 Nov 2008 $697,699
5 23 Feb 2009 $697,699
6 23 May 2009 $697,699
7 23 Aug 2009 $697,699
Phase 1 agreed $4,186,195
PHASE 1 ACTUAL DISBURSEMENTS
Disbursement Date Amount
1 7 Dec 2007 $188,874
SRL-607-G07-T - 1 7 Dec 2007 $634,900
SRL-607-G07-T - 1.1 7 Dec 2007 $50,000
2 11 May 2009 $436,121
SRL-607-G07-T - 2 18 Aug 2009 $300,774
SRL-607-G07-T - 3 23 Mar 2010 $1,236,173
SRL-607-G07-T - 3.1 23 Mar 2010 $14,025
SRL-607-G07-T - 3.2 23 Mar 2010 $50,000
Disbursed $2,910,868 (70% of total)
Undisbursed $1,275,327 (30% of total)
LATER EXPECTED DISBURSEMENTS
Disbursement Date Amount
Schedule not yet known
Agreed Amount $3,239,999
LATER ACTUAL DISBURSEMENTS
Disbursement Date Amount
None
Disbursed $0 (0% of total)
Undisbursed $3,239,999 (100% of total)
GROUP PERFORMANCE
Time from Phase 1 Approval to Agreement 7.6 months (26.8% of grants took less time; 73.2% took more time)
Time from Agreement to first disbursement 5.6 months. (67.9% of grants took less time, 32.1% took more time)
Most recent disbursement The most recent disbursement was 12.4 months behind schedule
Next disbursement The next disbursement is 2.3 months overdue
Phase 1 performance
D: This group is currently 14.7 months behind schedule. (87.2% of grants are doing better; 12.8% are doing worse)
The Global Fund bears no responsibility for this analysis. The computation of months ahead of or behind schedule was conducted by Aidspan using disbursement data obtained from the Global Fund's website. The Expected Disbursements reflect the Global Fund's standardized assumptions of what percentage of the grant is disbursed each three months. See Aidspan's Evaluation Methodology for more information.