Grant Details, Analysis and Evaluation
Global Fund Grants to Comoros as of 31 August 2010

The information provided here is based on data available from the Global Fund website. Based on that data, we provide a comparative evaluation of how each grant performed during its first 2 years (Phase 1). Performance information for later years is also provided but has not been evaluated. Aidspan is currently developing a more comprehensive evaluation methodology which will provide comparative analyses of grant performance during every phase: Phase 1 (Years 1-2), Phase 2 (Years 3-5) and Rolling Continuation Channel (RCC) covering subsequent years.

All money amounts are in US dollars. Grants are rated by Aidspan according to the following color-coded scheme:
A: On or ahead of schedule
B: Up to 3 months behind
C: 3 to 6 months behind
D: Over 6 months behind
N: Not rated

Global Fund grants to Comoros
4 grants, worth a total of $21,537,273, as follows:
Phase 1 - Years 1-2 Year 3 Onwards Total
HIV/AIDS$3,077,243 (approved) $2,114,945 (projected) $5,192,188 (projected)
Malaria$7,438,865 (agreed) $8,906,220 (projected) $16,345,085 (projected)
Total $10,516,108 (approved)$11,021,165 (projected)$21,537,273 (projected)
Disbursed $6,416,227 (61%)$1,337,465 (12%)$7,753,693 (36%)
Performance of Comoros grants
A: Grants on or ahead of schedule
1
A:On average, the Comoros grants are 0.5 months ahead of schedule
B: Grants up to 3 months behind schedule
1
C: Grants 3 to 6 months behind schedule
0
D: Grants over 6 months behind schedule
1
N: Grants not rated by Aidspan
1
Total number of grants:
4
Global Fund links for Comoros
Data regarding HIV/AIDS, TB and malaria in Comoros

In the table below, click on any grant to see that grant's background details and progress to date

Round /
NSA Wave
Disease Component
Applicant
Title Grant Number
(Click for details)
Principal Recipient Current Status
Phase 1 - Years 1-2
Phase 2 - Years 3-5
Phase 1 + Phase 2
Disbursed so far
Phase 1 rating:
Months ahead of or behind schedule
Round 2
Malaria
CCM
The fight against malaria at the community level in the Union of the Comoros COM-202-G01-M Association Comorienne pour le Bien-Etre de la Famille (ASCOBEF) Phase 1 approved. Agreement signed. Fully disbursed.
Phase 2 approved. Agreement signed. 93% disbursed.
P1 (agreed) : $1,534,631
P2 (agreed) : $951,247
P1+P2 (agreed) : $2,485,878
Disbursed: $2,422,471
D: 6.8 months behind
Round 3
HIV/AIDS
CCM
Prevention of STDs and HIV/AIDS among youth and adolescents in the Union of the Comoros Islands COM-304-G02-H Association Comorienne pour le Bien-Etre de la Famille (ASCOBEF) Phase 1 approved. Agreement signed. Fully disbursed.
Phase 2 approved. Agreement signed. 99% disbursed.
P1 (agreed) : $685,600
P2 (agreed) : $452,988
P1+P2 (agreed) : $1,138,588
Disbursed: $1,135,226
B: 2.8 months behind
Round 8
Malaria
CCM
Scale Up Interventions to Fight against Malaria in the Union of the Comoros COM-810-G03-M Association Comorienne pour le Bien-Etre de la Famille (ASCOBEF) Phase 1 approved. Agreement signed. 71% disbursed.
Phase 2 not yet approved. No disbursements yet.
P1 (agreed) : $5,904,234
P2 (projected) : $7,954,973
P1+P2 (projected) : $13,859,207
Disbursed: $4,195,996
A: 11.1 months ahead
Round 9
HIV/AIDS
CCM
Not yet known Round 9 HIV/AIDS Not yet known Phase 1 approved. Agreement not yet signed. No disbursements yet.
Phase 2 not yet approved. No disbursements yet.
P1 (approved) : $2,391,643
P2 (projected) : $1,661,957
P1+P2 (projected) : $4,053,600
Disbursed: $0
N: not yet rated

Round 1 grants were approved by the Fund's board on 24 April 2002, Round 2 grants were approved on 31 January 2003, Round 3 grants were approved on 17 October 2003, Round 4 grants were approved on 30 June 2004, Round 5 grants were approved on 30 September 2005, Round 6 grants were approved on 3 November 2006, Round 7 grants were approved on 13 November 2007, Round 8 grants were approved on 8 November 2008, Round 9 grants were approved on 11 November 2009, and Wave 1 NSA grants were approved on 11 November 2009

The Global Fund bears no responsibility for this analysis. The computation of months ahead of or behind schedule was conducted by Aidspan using disbursement data obtained from the Global Fund's website.