Global Fund Grants to Bhutan as of 31 August 2010

The information provided here is based on data available from the Global Fund website. Based on that data, we provide a comparative evaluation of how each grant performed during its first 2 years (Phase 1). Performance information for later years is also provided but has not been evaluated. Aidspan is currently developing a more comprehensive evaluation methodology which will provide comparative analyses of grant performance during every phase: Phase 1 (Years 1-2), Phase 2 (Years 3-5) and Rolling Continuation Channel (RCC) covering subsequent years.

All money amounts are in US dollars. Grants are rated by Aidspan according to the following color-coded scheme:
A: On or ahead of schedule
B: Up to 3 months behind
C: 3 to 6 months behind
D: Over 6 months behind
N: Not rated

Global Fund grants to Bhutan
5 grants, worth a total of $9,212,179, as follows:
Phase 1 - Years 1-2 Year 3 Onwards Total
HIV/AIDS$1,502,445 (agreed) $942,408 (agreed) $2,444,853 (agreed)
TB$1,302,257 (agreed) $774,955 (agreed) $2,077,212 (agreed)
Malaria$3,047,943 (agreed) $1,642,171 (approved) $4,690,114 (approved)
Total $5,852,645 (agreed)$3,359,534 (approved)$9,212,179 (approved)
Disbursed $5,750,458 (98%)$867,554 (26%)$6,618,012 (72%)
Performance of Bhutan grants
A: Grants on or ahead of schedule
2
B:On average, the Bhutan grants are 2.8 months behind schedule
B: Grants up to 3 months behind schedule
0
C: Grants 3 to 6 months behind schedule
1
D: Grants over 6 months behind schedule
2
N: Grants not rated by Aidspan
0
Total number of grants:
5
Global Fund links for Bhutan
Data regarding HIV/AIDS, TB and malaria in Bhutan

In the table below, click on any grant to see that grant's background details and progress to date

Round /
NSA Wave
Disease Component
Applicant
Title Grant Number
(Click for details)
Principal Recipient Current Status
Phase 1 - Years 1-2
Phase 2 - Years 3-5
Phase 1 + Phase 2
Disbursed so far
Phase 1 rating:
Months ahead of or behind schedule
Round 4
Malaria
CCM
Enhanced Malaria Control Project BTN-405-G01-M Gross National Happiness (GNH) Commission, Royal Government of Bhutan Phase 1 approved. Agreement signed. Fully disbursed.
Phase 2 approved. Agreement signed. 46% disbursed.
P1 (agreed) : $1,000,957
P2 (agreed) : $736,233
P1+P2 (agreed) : $1,737,190
Disbursed: $1,343,198
A: 5.4 months ahead
Round 4
TB
CCM
Impending Crisis of Malaria & TB: A Renewed Strategy to Reduce Malaria, TB Disease Burden in Bhutan BTN-405-G02-T Gross National Happiness (GNH) Commission, Royal Government of Bhutan Phase 1 approved. Agreement signed. Fully disbursed.
Phase 2 approved. Agreement signed. 75% disbursed.
P1 (agreed) : $560,568
P2 (agreed) : $433,730
P1+P2 (agreed) : $994,298
Disbursed: $886,470
A: 5.3 months ahead
Round 6
HIV/AIDS
CCM
Scaling-up HIV prevention services among youth and other vulnerable population groups through multi sectoral approach BTN-607-G03-H Gross National Happiness (GNH) Commission, Royal Government of Bhutan Phase 1 approved. Agreement signed. Fully disbursed.
Phase 2 approved. Agreement signed. 21% disbursed.
P1 (agreed) : $1,502,445
P2 (agreed) : $942,408
P1+P2 (agreed) : $2,444,853
Disbursed: $1,701,857
D: 8.1 months behind
Round 6
TB
CCM
Strengthening Quality TB Control in Bhutan BTN-607-G04-T Gross National Happiness (GNH) Commission, Royal Government of Bhutan Phase 1 approved. Agreement signed. 96% disbursed.
Phase 2 approved. Agreement signed. No disbursements yet.
P1 (agreed) : $741,689
P2 (agreed) : $341,225
P1+P2 (agreed) : $1,082,914
Disbursed: $708,375
D: 12.6 months behind
Round 7
Malaria
CCM
Strengthening Malaria Prevention and Control in Bhutan BTN-708-G05-M Gross National Happiness (GNH) Commission, Royal Government of Bhutan Phase 1 approved. Agreement signed. 97% disbursed.
Phase 2 approved. Agreement not yet signed, No disbursements yet.
P1 (agreed) : $2,046,986
P2 (approved) : $905,938
P1+P2 (approved) : $2,952,924
Disbursed: $1,978,113
C: 3.9 months behind

Round 1 grants were approved by the Fund's board on 24 April 2002, Round 2 grants were approved on 31 January 2003, Round 3 grants were approved on 17 October 2003, Round 4 grants were approved on 30 June 2004, Round 5 grants were approved on 30 September 2005, Round 6 grants were approved on 3 November 2006, Round 7 grants were approved on 13 November 2007, Round 8 grants were approved on 8 November 2008, Round 9 grants were approved on 11 November 2009, and Wave 1 NSA grants were approved on 11 November 2009