An independent watchdog of the Global Fund and publisher of Global Fund Observer

Grant Details, Analysis and Evaluation
Global Fund Grants to Morocco as of 31 August 2010

The information provided here is based on data available from the Global Fund website. Based on that data, we provide a comparative evaluation of how each grant performed during its first 2 years (Phase 1). Performance information for later years is also provided but has not been evaluated. Aidspan is currently developing a more comprehensive evaluation methodology which will provide comparative analyses of grant performance during every phase: Phase 1 (Years 1-2), Phase 2 (Years 3-5) and Rolling Continuation Channel (RCC) covering subsequent years.

All money amounts are in US dollars. Grants are rated by Aidspan according to the following color-coded scheme:
A: On or ahead of schedule
B: Up to 3 months behind
C: 3 to 6 months behind
D: Over 6 months behind
N: Not rated

Global Fund grants to Morocco
3 grants, worth a total of $38,273,153, as follows:
Phase 1 - Years 1-2 Year 3 Onwards Total
HIV/AIDS$15,419,604 (agreed) $18,695,749 (agreed) $34,115,353 (agreed)
TB$2,221,975 (agreed) $1,935,825 (agreed) $4,157,800 (agreed)
Total $17,641,579 (agreed)$20,631,574 (agreed)$38,273,153 (agreed)
Disbursed $17,641,579 (100%)$9,944,084 (48%)$27,585,663 (72%)
Performance of Morocco grants
A: Grants on or ahead of schedule
0
C:On average, the Morocco grants are 4.4 months behind schedule
B: Grants up to 3 months behind schedule
1
C: Grants 3 to 6 months behind schedule
1
D: Grants over 6 months behind schedule
1
N: Grants not rated by Aidspan
0
Total number of grants:
3
Global Fund links for Morocco
Data regarding HIV/AIDS, TB and malaria in Morocco

In the table below, click on any grant to see that grant's background details and progress to date

Round /
NSA Wave
Disease Component
Applicant
Title Grant Number
(Click for details)
Principal Recipient Current Status
Phase 1 - Years 1-2
Phase 2 - Years 3-5
Phase 1 + Phase 2
Disbursed so far
Phase 1 rating:
Months ahead of or behind schedule
Round 1
HIV/AIDS
CCM
Support for the Implementation of the National Strategic Plan to Fight AIDS MOR-102-G01-H The Ministry of Health of the Government of the Kingdom of Morocco Phase 1 approved. Agreement signed. Fully disbursed.
Phase 2 approved. Agreement signed. Fully disbursed.
P1 (agreed) : $4,738,806
P2 (agreed) : $4,499,948
P1+P2 (agreed) : $9,238,754
Disbursed: $9,230,662
B: 3.0 months behind
Round 6
HIV/AIDS
CCM
Programme d'appui à l'extension de la stratégie nationale de lutte contre le VIH/SIDA au Maroc MOR-607-G02-H The Ministry of Health of the Government of the Kingdom of Morocco Phase 1 approved. Agreement signed. Fully disbursed.
Phase 2 approved. Agreement signed. 35% disbursed.
P1 (agreed) : $10,680,798
P2 (agreed) : $14,195,801
P1+P2 (agreed) : $24,876,599
Disbursed: $15,697,065
C: 3.8 months behind
Round 6
TB
CCM
Appui à la mise en œuvre du plan stratégique national de lutte contre la Tuberculose 2006-2015 MOR-607-G03-T The Ministry of Health of the Government of the Kingdom of Morocco Phase 1 approved. Agreement signed. Fully disbursed.
Phase 2 approved. Agreement signed. 23% disbursed.
P1 (agreed) : $2,221,975
P2 (agreed) : $1,935,825
P1+P2 (agreed) : $4,157,800
Disbursed: $2,657,936
D: 6.5 months behind

Round 1 grants were approved by the Fund's board on 24 April 2002, Round 2 grants were approved on 31 January 2003, Round 3 grants were approved on 17 October 2003, Round 4 grants were approved on 30 June 2004, Round 5 grants were approved on 30 September 2005, Round 6 grants were approved on 3 November 2006, Round 7 grants were approved on 13 November 2007, Round 8 grants were approved on 8 November 2008, Round 9 grants were approved on 11 November 2009, and Wave 1 NSA grants were approved on 11 November 2009

The Global Fund bears no responsibility for this analysis. The computation of months ahead of or behind schedule was conducted by Aidspan using disbursement data obtained from the Global Fund's website.