An independent watchdog of the Global Fund and publisher of Global Fund Observer

Grant Details, Analysis and Evaluation
Global Fund Grants to Cuba as of 31 August 2010

The information provided here is based on data available from the Global Fund website. Based on that data, we provide a comparative evaluation of how each grant performed during its first 2 years (Phase 1). Performance information for later years is also provided but has not been evaluated. Aidspan is currently developing a more comprehensive evaluation methodology which will provide comparative analyses of grant performance during every phase: Phase 1 (Years 1-2), Phase 2 (Years 3-5) and Rolling Continuation Channel (RCC) covering subsequent years.

All money amounts are in US dollars. Grants are rated by Aidspan according to the following color-coded scheme:
A: On or ahead of schedule
B: Up to 3 months behind
C: 3 to 6 months behind
D: Over 6 months behind
N: Not rated

Global Fund grants to Cuba
3 grants, worth a total of $69,893,415, as follows:
Phase 1 - Years 1-2 Year 3 Onwards Total
HIV/AIDS$25,834,872 (agreed) $36,186,945 (agreed) $62,021,817 (agreed)
TB$5,455,745 (agreed) $2,415,853 (projected) $7,871,598 (projected)
Total $31,290,617 (agreed)$38,602,798 (projected)$69,893,415 (projected)
Disbursed $30,915,527 (99%)$23,560,020 (61%)$54,475,547 (78%)
Performance of Cuba grants
A: Grants on or ahead of schedule
2
B:On average, the Cuba grants are 0.6 months behind schedule
B: Grants up to 3 months behind schedule
0
C: Grants 3 to 6 months behind schedule
0
D: Grants over 6 months behind schedule
1
N: Grants not rated by Aidspan
0
Total number of grants:
3
Global Fund links for Cuba
Data regarding HIV/AIDS, TB and malaria in Cuba

In the table below, click on any grant to see that grant's background details and progress to date

Round /
NSA Wave
Disease Component
Applicant
Title Grant Number
(Click for details)
Principal Recipient Current Status
Phase 1 - Years 1-2
Phase 2 - Years 3-5
Phase 1 + Phase 2
Disbursed so far
Phase 1 rating:
Months ahead of or behind schedule
Round 2
HIV/AIDS
CCM
Strengthening the multi-sector national response to prevent and address the HIV/AIDS epidemic in the Republic of Cuba CUB-202-G01-H The United Nations Development Programme Phase 1 approved. Agreement signed. Fully disbursed.
Phase 2 approved. Agreement signed. 83% disbursed.
P1 (agreed) : $11,465,129
P2 (agreed) : $24,759,833
P1+P2 (agreed) : $36,224,962
Disbursed: $31,954,128
A: 5.2 months ahead
Round 6
HIV/AIDS
CCM
Expansion and decentralisation of actions for HIV/AIDS prevention and comprehensive care and support for PLWHA in Cuba CUB-607-G02-H The United Nations Development Programme Phase 1 approved. Agreement signed. Fully disbursed.
Phase 2 approved. Agreement signed. 27% disbursed.
P1 (agreed) : $14,369,743
P2 (agreed) : $11,427,112
P1+P2 (agreed) : $25,796,855
Disbursed: $17,440,764
D: 8.1 months behind
Round 7
TB
CCM
Strengthening the Tuberculosis Control Programme In the Republic of Cuba CUB-708-G03-T The United Nations Development Programme Phase 1 approved. Agreement signed. 93% disbursed.
Phase 2 not yet approved. No disbursements yet.
P1 (agreed) : $5,455,745
P2 (projected) : $2,415,853
P1+P2 (projected) : $7,871,598
Disbursed: $5,080,655
A: 1.1 months ahead

Round 1 grants were approved by the Fund's board on 24 April 2002, Round 2 grants were approved on 31 January 2003, Round 3 grants were approved on 17 October 2003, Round 4 grants were approved on 30 June 2004, Round 5 grants were approved on 30 September 2005, Round 6 grants were approved on 3 November 2006, Round 7 grants were approved on 13 November 2007, Round 8 grants were approved on 8 November 2008, Round 9 grants were approved on 11 November 2009, and Wave 1 NSA grants were approved on 11 November 2009

The Global Fund bears no responsibility for this analysis. The computation of months ahead of or behind schedule was conducted by Aidspan using disbursement data obtained from the Global Fund's website.