Global Fund Grants to Gabon as of 31 August 2010

The information provided here is based on data available from the Global Fund website. Based on that data, we provide a comparative evaluation of how each grant performed during its first 2 years (Phase 1). Performance information for later years is also provided but has not been evaluated. Aidspan is currently developing a more comprehensive evaluation methodology which will provide comparative analyses of grant performance during every phase: Phase 1 (Years 1-2), Phase 2 (Years 3-5) and Rolling Continuation Channel (RCC) covering subsequent years.

All money amounts are in US dollars. Grants are rated by Aidspan according to the following color-coded scheme:
A: On or ahead of schedule
B: Up to 3 months behind
C: 3 to 6 months behind
D: Over 6 months behind
N: Not rated

Global Fund grants to Gabon
4 grants, divided into 6 sub-grants, worth a total of $55,681,477, as follows:
Phase 1 - Years 1-2 Year 3 Onwards Total
HIV/AIDS$13,884,260 (agreed) $19,625,911 (projected) $33,510,171 (projected)
Malaria$11,579,947 (agreed) $10,591,359 (approved) $22,171,306 (approved)
Total $25,464,207 (agreed)$30,217,270 (projected)$55,681,477 (projected)
Disbursed $20,893,193 (82%)$5,781,224 (19%)$26,674,416 (48%)
Performance of Gabon grants
A: Grants on or ahead of schedule
1
D:On average, the rated Gabon grants are 8.2 months behind schedule
B: Grants up to 3 months behind schedule
0
C: Grants 3 to 6 months behind schedule
1
D: Grants over 6 months behind schedule
2
N: Grants not rated by Aidspan
0
Total number of grants:
4
Global Fund links for Gabon
Data regarding HIV/AIDS, TB and malaria in Gabon

In the table below, click on any grant to see that grant's background details and progress to date

Round /
NSA Wave
Disease Component
Applicant
Title Grant Number
(Click for details)
Principal Recipient Current Status
Phase 1 - Years 1-2
Phase 2 - Years 3-5
Phase 1 + Phase 2
Disbursed so far
Phase 1 rating:
Months ahead of or behind schedule
Round 3
HIV/AIDS
CCM
Strengthening the Gabon initiative on fighting HIV/AIDS
The United Nations Development Programme
Phase 1 approved. Agreement signed. Fully disbursed.
Phase 2 approved. Agreement signed. 7% disbursed.
P1 (agreed) : $6,309,000
P2 (agreed) : $7,790,726
P1+P2 (agreed) : $14,099,726
Disbursed: $6,890,482
D: 25.7 months behind
Round 5
Malaria
CCM
Faire Reculer le Paludisme Gabon
1) Ministry of Health and Public Hygiene of the Governemnt of the Gabonese Republic
2) The United Nations Development Programme
Phase 1 approved. Agreement signed. Fully disbursed.
Phase 2 approved. Agreement not yet signed, 43% disbursed.
P1 (agreed) : $4,160,323
P2 (approved) : $9,394,661
P1+P2 (approved) : $13,554,984
Disbursed: $8,163,366
C: 5.4 months behind
Round 4
Malaria
CCM
FAIRE RECULER LE PALUDISME GABON GAB-404-G02-M The United Nations Development Programme Phase 1 approved. Agreement signed. Fully disbursed.
Phase 2 approved. Agreement signed. Fully disbursed.
P1 (agreed) : $7,419,624
P2 (agreed) : $1,196,698
P1+P2 (agreed) : $8,616,322
Disbursed: $8,616,322
D: 6.2 months behind
Round 8
HIV/AIDS
CCM
Support to the Gabonese initiative to fight AIDS GAB-809-G05-H Ministry of Health and Public Hygiene of the Governemnt of the Gabonese Republic Phase 1 approved. Agreement signed. 40% disbursed.
Phase 2 not yet approved. No disbursements yet.
P1 (agreed) : $7,575,260
P2 (projected) : $11,835,185
P1+P2 (projected) : $19,410,445
Disbursed: $3,004,246
A: 4.6 months ahead

Round 1 grants were approved by the Fund's board on 24 April 2002, Round 2 grants were approved on 31 January 2003, Round 3 grants were approved on 17 October 2003, Round 4 grants were approved on 30 June 2004, Round 5 grants were approved on 30 September 2005, Round 6 grants were approved on 3 November 2006, Round 7 grants were approved on 13 November 2007, Round 8 grants were approved on 8 November 2008, Round 9 grants were approved on 11 November 2009, and Wave 1 NSA grants were approved on 11 November 2009