Global Fund grants to Lesotho |
8 grants, divided into 9 sub-grants, worth a total of $216,245,848, as follows:
|
Phase 1 - Years 1-2
|
Year 3 Onwards
|
Total
|
| HIV/AIDS | $98,373,750 (approved)
| $84,207,362 (projected)
| $182,581,112 (projected)
|
| TB | $13,535,674 (agreed)
| $20,129,062 (projected)
| $33,664,736 (projected)
|
|
Total
| $111,909,424 (approved) | $104,336,424 (projected) | $216,245,848 (projected) |
|
Disbursed
| $50,880,857 (45%) | $27,043,220 (26%) | $77,924,077 (36%) |
|
|
Performance of
Lesotho grants
|
|
A: Grants on or ahead of schedule
|
1
|
| D: | On average, the rated Lesotho grants are 9.5 months behind schedule |
|
|
B: Grants up to 3 months behind schedule
|
0
|
|
C: Grants 3 to 6 months behind schedule
|
0
|
|
D: Grants over 6 months behind schedule
|
5
|
|
N: Grants not rated by Aidspan
|
2
|
|
Total number of grants:
|
8
|
|
|
Global Fund links for Lesotho |
|
|
Data regarding HIV/AIDS, TB and malaria in Lesotho
|
|
In the table below, click on any grant to see that grant's background details and progress to date
Round / NSA Wave
|
|
Disease Component
|
|
Applicant
|
|
Title
|
Grant Number (Click for details)
|
Principal Recipient
|
Current Status
|
|
Phase 1 - Years 1-2
|
|
Phase 2 - Years 3-5
|
|
Phase 1 + Phase 2
|
|
Disbursed so far
|
|
Phase 1 rating:
Months ahead of or behind schedule
|
|
|
Stepping Up Universal Access: A Multi-Sectoral partnership Response to HIV at the Community Level |
|
1) The Ministry of Finance and Development Planning of the Government of the Kingdom of Lesotho
2) Lesotho Council of Non-Governmental Organizations |
Phase 1 approved. Agreement signed. 31% disbursed. Phase 2 approved. Agreement not yet signed, No disbursements yet.
|
| P1 (agreed) : |
$56,820,590 |
| P2 (approved) : |
$23,994,466 |
| P1+P2 (approved) : |
$80,815,056 |
| Disbursed: |
$17,433,859 |
|
|
|
|
Not yet known |
LSO-810-G08-T |
The Ministry of Finance and Development Planning of the Government of the Kingdom of Lesotho |
Phase 1 approved. Agreement signed. No disbursements yet. Phase 2 not yet approved. No disbursements yet.
|
| P1 (agreed) : |
$7,736,869 |
| P2 (projected) : |
$15,384,062 |
| P1+P2 (projected) : |
$23,120,931 |
| Disbursed: |
$0 |
|
|
|
|
Strengthening Prevention & Control of HIV/AIDS in Lesotho |
LSO-202-G01-H |
The Ministry of Finance and Development Planning of the Government of the Kingdom of Lesotho |
Phase 1 approved. Agreement signed. Fully disbursed. Phase 2 approved. Agreement signed. 98% disbursed.
|
| P1 (agreed) : |
$10,557,000 |
| P2 (agreed) : |
$18,755,000 |
| P1+P2 (agreed) : |
$29,312,000 |
| Disbursed: |
$28,884,104 |
|
|
|
|
Strengthening TB Prevention and Control in Lesotho |
LSO-202-G02-T |
The Ministry of Finance and Development Planning of the Government of the Kingdom of Lesotho |
Phase 1 approved. Agreement signed. Fully disbursed. Phase 2 approved. Agreement signed. 98% disbursed.
|
| P1 (agreed) : |
$2,000,000 |
| P2 (agreed) : |
$3,000,000 |
| P1+P2 (agreed) : |
$5,000,000 |
| Disbursed: |
$4,947,928 |
|
|
|
|
Scaling up HIV/AIDS prevention, care and treatment interventions and a viable health system for their implementation |
LSO-506-G03-H |
The Ministry of Finance and Development Planning of the Government of the Kingdom of Lesotho |
Phase 1 approved. Agreement signed. Fully disbursed. Phase 2 approved. Agreement signed. Fully disbursed.
|
| P1 (agreed) : |
$10,013,383 |
| P2 (agreed) : |
$5,768,189 |
| P1+P2 (agreed) : |
$15,781,572 |
| Disbursed: |
$15,781,572 |
|
|
|
|
Reducing morbidity and mortality due to Tuberculosis by community involvement in TB control |
LSO-607-G04-T |
The Ministry of Finance and Development Planning of the Government of the Kingdom of Lesotho |
Phase 1 approved. Agreement signed. 84% disbursed. Phase 2 approved. Agreement signed. No disbursements yet.
|
| P1 (agreed) : |
$3,798,805 |
| P2 (agreed) : |
$1,745,000 |
| P1+P2 (agreed) : |
$5,543,805 |
| Disbursed: |
$3,180,858 |
|
|
|
|
Preventing HIV and Mitigating the Impact of AIDS Among Orphans and Vulnerable Children In Lesotho |
LSO-708-G05-H |
The Ministry of Finance and Development Planning of the Government of the Kingdom of Lesotho |
Phase 1 approved. Agreement signed. 72% disbursed. Phase 2 approved. Agreement not yet signed, No disbursements yet.
|
| P1 (agreed) : |
$10,626,665 |
| P2 (approved) : |
$15,249,526 |
| P1+P2 (approved) : |
$25,876,191 |
| Disbursed: |
$7,695,757 |
|
|
|
|
Not yet known |
Round 9 HIV/AIDS |
Not yet known |
Phase 1 approved. Agreement not yet signed. No disbursements yet. Phase 2 not yet approved. No disbursements yet.
|
| P1 (approved) : |
$10,356,112 |
| P2 (projected) : |
$20,440,181 |
| P1+P2 (projected) : |
$30,796,293 |
| Disbursed: |
$0 |
|
|