Global Fund Grants to Angola as of 31 August 2010

The information provided here is based on data available from the Global Fund website. Based on that data, we provide a comparative evaluation of how each grant performed during its first 2 years (Phase 1). Performance information for later years is also provided but has not been evaluated. Aidspan is currently developing a more comprehensive evaluation methodology which will provide comparative analyses of grant performance during every phase: Phase 1 (Years 1-2), Phase 2 (Years 3-5) and Rolling Continuation Channel (RCC) covering subsequent years.

All money amounts are in US dollars. Grants are rated by Aidspan according to the following color-coded scheme:
A: On or ahead of schedule
B: Up to 3 months behind
C: 3 to 6 months behind
D: Over 6 months behind
N: Not rated

Global Fund grants to Angola
5 grants, worth a total of $236,258,097, as follows:
Phase 1 - Years 1-2 Year 3 Onwards Total
HIV/AIDS$27,670,810 (agreed) $58,449,405 (agreed) $86,120,215 (agreed)
TB$18,734,904 (approved) $17,902,484 (projected) $36,637,388 (projected)
Malaria$60,986,002 (agreed) $52,514,492 (projected) $113,500,494 (projected)
Total $107,391,716 (approved)$128,866,381 (projected)$236,258,097 (projected)
Disbursed $90,376,258 (84%)$36,599,117 (28%)$126,975,375 (54%)
Performance of Angola grants
A: Grants on or ahead of schedule
0
D:On average, the rated Angola grants are 10.8 months behind schedule
B: Grants up to 3 months behind schedule
0
C: Grants 3 to 6 months behind schedule
1
D: Grants over 6 months behind schedule
3
N: Grants not rated by Aidspan
1
Total number of grants:
5
Global Fund links for Angola
Data regarding HIV/AIDS, TB and malaria in Angola

In the table below, click on any grant to see that grant's background details and progress to date

Round /
NSA Wave
Disease Component
Applicant
Title Grant Number
(Click for details)
Principal Recipient Current Status
Phase 1 - Years 1-2
Phase 2 - Years 3-5
Phase 1 + Phase 2
Disbursed so far
Phase 1 rating:
Months ahead of or behind schedule
Round 3
Malaria
CCM
Angolan Proposal to fight HIV/AIDS, Malaria and Tuberculosis AGO-305-G01-M The United Nations Development Programme Phase 1 approved. Agreement signed. Fully disbursed.
Phase 2 approved. Agreement signed. 97% disbursed.
P1 (agreed) : $28,473,354
P2 (agreed) : $6,556,518
P1+P2 (agreed) : $35,029,872
Disbursed: $34,833,588
D: 10.1 months behind
Round 4
HIV/AIDS
CCM
Reducing the burden of HIV/AIDS AGO-405-G03-H The United Nations Development Programme Phase 1 approved. Agreement signed. Fully disbursed.
Phase 2 approved. Agreement signed. 47% disbursed.
P1 (agreed) : $27,670,810
P2 (agreed) : $58,449,405
P1+P2 (agreed) : $86,120,215
Disbursed: $54,941,594
D: 12.2 months behind
Round 4
TB
CCM
Reducing the burden of Tuberculosis AGO-405-G02-T The United Nations Development Programme Phase 1 approved. Agreement signed. Fully disbursed.
Phase 2 approved. Agreement signed. 84% disbursed.
P1 (agreed) : $7,350,590
P2 (agreed) : $3,520,436
P1+P2 (agreed) : $10,871,026
Disbursed: $10,318,689
D: 17.2 months behind
Round 7
Malaria
CCM
Scaling Up Malaria Interventions In Angola AGO-708-G04-M Ministry of Health of the Government of the Republic of Angola Phase 1 approved. Agreement signed. 83% disbursed.
Phase 2 not yet approved. No disbursements yet.
P1 (agreed) : $32,512,648
P2 (projected) : $45,957,974
P1+P2 (projected) : $78,470,622
Disbursed: $26,881,504
C: 3.9 months behind
Round 9
TB
CCM
Not yet known Round 9 TB Not yet known Phase 1 approved. Agreement not yet signed. No disbursements yet.
Phase 2 not yet approved. No disbursements yet.
P1 (approved) : $11,384,314
P2 (projected) : $14,382,048
P1+P2 (projected) : $25,766,362
Disbursed: $0
N: not yet rated

Round 1 grants were approved by the Fund's board on 24 April 2002, Round 2 grants were approved on 31 January 2003, Round 3 grants were approved on 17 October 2003, Round 4 grants were approved on 30 June 2004, Round 5 grants were approved on 30 September 2005, Round 6 grants were approved on 3 November 2006, Round 7 grants were approved on 13 November 2007, Round 8 grants were approved on 8 November 2008, Round 9 grants were approved on 11 November 2009, and Wave 1 NSA grants were approved on 11 November 2009

The Global Fund bears no responsibility for this analysis. The computation of months ahead of or behind schedule was conducted by Aidspan using disbursement data obtained from the Global Fund's website.